Posts

FXB Engineering MEP www.fxbinc.com

SOLAR GENERATING PLANT ST. THOMAS, USVI

FXB Engineering Announces Implementation of a Solar Generating Plant for St. Thomas, USVI that will provide up to 5% of the Islands Energy Source

FXB Engineering provides high level of reliability on VIWAPA’s transmission systems for generation resources.

FXB Engineering, a leading provider of Mechanical, Electrical, Plumbing and Fire Protection engineering services, promotes our continued engineering services provided to The Virgin Islands Water and Power Authority. “FXB implemented a new 34.5kV Gas Insulated Switchgear (GIS) substation located in the Power Distribution Center (PDC) to tie in the 5 MW of solar power into the utility companies transmission system. We are excited to be a part of this project. The newly installed solar farm will provide 4-5% of St Thomas’s current base load capacity during daylight hours. FXB provided a robust double bus 34.5kV GIS design with primary and backup protection for the transmission lines in order to maintain a high level of reliability on VIWAPA’s transmission system,” states Peter J. Bonnes, President at FXB Engineering.

The Virgin Islands Water and Power Authority and Main Street Power Company hosted the dedication ceremonies last month for the new solar power generation plant in Estate Donoe on St. Thomas. The new facility was tested and peaked at 4.2MW. WAPA chief executive officer and executive director Hugo V. Hodge, Jr. said the addition of the solar farm and a similar installation on St. Croix, which was dedicated in 2014, continues the authority’s effort to diversify its generation resources. For more information see article: Electrical Construction and Maintenance, March 12, 2015, WAPA, Main Street Power and Morgan Stanley Commission Solar Photovoltaic Project.
http://ecmweb.com/green-building/wapa-main-street-power-and-morgan-stanley-commission-solar-photovoltaic-project

FXB Engineering MEP www.fxbinc.com

BASE STATION HOTEL, TRANSIT WIRELESS

Client: Base Station Hotels, Transit Wireless, Manhattan, NY
Purpose: MEP improvements to mission critical data center.  
Highlights: Transit Wireless recently completed the build out of its wireless and Wi-Fi network in all 30 of the MTA’s underground subway stations in the borough. FXB provided MEP for 5,000 – 6,000 s.f  fit-outs for communication equipment and A&E documentation.

Project: Completed in 2012, 2014 and 2015.
Project budget: $7.4 million