LARGE BROADCASTING COMPANY

Critical Power Systems Upgrade
Purpose: To replace end of life Critical Power Infrastructure and to improve overall reliability and maintainability of critical power systems.

Highlights: Replace 800kW Rotary UPS with two (2) new redundant 1100kW UPS systems. Replace (3) 750kW generators with (3) 1500 kW generators and paralleling switchgear. Phased project to allow for one complete UPS system to be installed, tested and fully commissioned prior to removing the existing system.

Time frame & Budget:
Phase I was completed in 2012; Phase II finished in 2015. Project stayed on budget at $9.9 million.

 


 

Purpose: To replace end of life mechanical equipment for critical facility and improve overall reliability and control.Highlights: Replace air cooled chillers, pumps & complete piping systems. Three (3) new 275 ton chillers. Three (3) new wet cell cooling towers. Phased project to allow for the new chiller plant to be installed, tested and fully commissioned while the existing mechanical equipment remained in place.

Project: Completed in 2014.
Project budget: $11 million