EAST BRANDYWINE TOWNSHIP MUNICIPAL BUILDING

EAST BRANDYWINE TOWNSHIP MUNICIPAL BUILDING
DOWNINGTOWN, PA


Project included the following:
• 22,000 SF Municipal building including Administrative space, Public
Meeting Room and Police Station
• 6,900 SF 6 bay Maintenance Garage with storage loft
• 2,000 SF salt shed
• New 150kW generator to support municipal building and maintenance
garage
• New 30KVA uninterruptible power system (UPS) for critical loads
• Municipal building mechanical systems consisted of chilled water system
and hydronic heating systems for maximum efficiency
• New electrical service & distribution for the entire site
• New site lighting
• New fuel pump dispensing station
• FXB provided MEP, FP & FA design services

Estimated project cost: $6.5 Million