Posts

FXB Engineering MEP www.fxbinc.com

RAYMOUR & FLANIGAN

MEP engineering fit-out design and C/A services for over forty locations in the North East including PA, NY, NJ, MA & RI.

FXB Engineering MEP www.fxbinc.com

IRONHILL BREWERY

MEP engineering design services for Iron Hill Brewery restaurants in Delaware, New Jersey & Pennsylvania.

FXB Engineering MEP www.fxbinc.com

BRICKHOUSE TAVERN & TAP

MEP engineering for complete tenant restaurant fit-out projects for Brick House Tavern & Tap.

FXB Engineering MEP www.fxbinc.com

CALVARY CHAPEL

FXB provided the MEP engineering services for the new construction of this three-story, 35,000 SF religious facility.

FXB Engineering MEP www.fxbinc.com

ST. DAVIDS GOLF CLUB

FXB provided MEP FP engineering design for the new construction of a 29,000 SF Golf Club building banquet, grill rooms & commercial kitchen.

FXB Engineering MEP www.fxbinc.com

LEHIGH COUNTRY CLUB

MEP engineering and design for over 25,000 SF of additions and renovations for this two-story club house.

FXB Engineering MEP www.fxbinc.com

PENNBROOK APARTMENTS

FXB provided the MEP engineering design services for this two-story,  23,200 SF apartment building.

FXB Engineering MEP www.fxbinc.com

LARGE BROADCASTING COMPANY

Critical Power Systems Upgrade
Purpose: To replace end of life Critical Power Infrastructure and to improve overall reliability and maintainability of critical power systems.

Highlights: Replace 800kW Rotary UPS with two (2) new redundant 1100kW UPS systems. Replace (3) 750kW generators with (3) 1500 kW generators and paralleling switchgear. Phased project to allow for one complete UPS system to be installed, tested and fully commissioned prior to removing the existing system.

Time frame & Budget:
Phase I was completed in 2012; Phase II finished in 2015. Project stayed on budget at $9.9 million.

 


 

Purpose: To replace end of life mechanical equipment for critical facility and improve overall reliability and control.Highlights: Replace air cooled chillers, pumps & complete piping systems. Three (3) new 275 ton chillers. Three (3) new wet cell cooling towers. Phased project to allow for the new chiller plant to be installed, tested and fully commissioned while the existing mechanical equipment remained in place.

Project: Completed in 2014.
Project budget: $11 million

FXB Engineering MEP www.fxbinc.com

KRANDO METAL PRODUCTS

KRANDO METAL PRODUCTS
BROOMALL, PA

Electrical design for the renovation of the electrical infrastructure.

Renovate the existing electrical infrastructure to allow Krando to support their state-of-the-art, high-end custom metal fabrication 75,000 S F facility. This high-end 75,000 SF metal manufacturing facility powers the largest and fastest laser cutting machines in the industry and required state-of-the-art electrical infrastructure. FXB provided the foundation for Krando to continue to be a leader in their
industry.